Two clocks, and they do not start together
A container that waits costs money twice, under two different names, billed by two different parties, and governed by two different clocks. Almost every dispute about these charges begins with someone treating them as one thing.
Demurrage is the container sitting in the terminal after its free time has expired, not yet collected. The clock starts at the port, the charge is levied by the carrier or the terminal operator, and it is triggered by the importer’s failure to move cargo out.
Detention is the container outside the terminal, not yet returned. The clock starts when the box leaves the gate, the charge is levied by whoever owns or leases the equipment, and it is triggered by the consignee’s failure to bring the empty back.
There are four versions of this in a single door-to-door movement, and each has its own free period. Laid out, they look like this.
| Box is in the terminal — demurrage | Box is with you — detention | |
|---|---|---|
| At origin | Rare: export boxes waiting at the load port beyond free time | Common: the box was collected for loading and returned late, so the factory’s loading window is the control |
| At destination | The expensive one: cargo discharged but not collected, billed to the importer | The one people forget: the empty sits on the chassis because nobody booked the return |
| Clock starts | When the box becomes available, not when the vessel berths | When the box leaves the gate on a laden move |
| Who pays | Whoever is the importer under the Incoterm | Whoever holds the equipment — usually the consignee |
A seller who only plans for the destination pair is planning for half the exposure, and the half they skipped is the one inside their own supplier’s control.
The clock starts when you can collect, not when the ship arrives
This is the single most useful fact in the whole subject. Free time runs from the point the container is available for collection — discharged, grounded, and notified — not from the vessel’s arrival date.
Which means the first question in any dispute is not “was the cargo late” but “when did the terminal actually make it available, and did anyone tell me”. A container discharged on a Friday but only grounded on a Monday has a clock that started on Monday. A container available but never notified, because the arrival notice went to an address nobody reads, has an argument attached to it.
The distinction also cuts the other way. Terminals do not pause their clock for a consignee’s convenience: if the appointment system is full for four days and the box is available throughout, the free time is being consumed. That is why the appointment record matters as much as the delivery order in a peak week — the same congestion that makes a slot scarce is described in why a November order misses Christmas — — it is the document that separates “the terminal could not give me a slot” from “I did not book one”.
The American rulebook changed, and half of it survived
In the United States these charges stopped being a purely contractual matter in 2024, when the Federal Maritime Commission’s rule on detention and demurrage billing practices took effect on 28 May, implementing the Ocean Shipping Reform Act of 2022.
Then, in September 2025, a federal appeals court set aside one section of that rule — the provision that limited who an invoice could be sent to. That section had restricted billing to the party that contracted for the transportation, or to the consignee, and prohibited invoicing both. It is gone.
Everything else survived, and this is the part shippers keep missing. The 30-day issuance deadline, the required contents of the invoice, and the dispute process all remain in force. The regulator’s own summary is blunt: carriers and terminal operators must continue to follow these requirements or risk being found in violation, and failing to meet the invoicing or content provisions eliminates any obligation of the billed party to pay.
The context explains why this regime exists at all: nine of the largest carriers collected about 8.9 billion dollars in detention and demurrage between 2020 and 2022. A charge designed to encourage cargo to move had become, in some lanes, a revenue line — which is what the “incentive principle” in the rule is meant to prevent.
Four ways an invoice stops being payable
Where the US rule applies, an invoice is not simply a bill. It is a document with conditions, and failing any of them removes the obligation rather than creating a negotiation.
- It arrived too late. Invoices must be issued within 30 calendar days from when the charges were last incurred. An NVOCC passing on a carrier’s charge gets 30 days from the date it received the upstream invoice, not from the original charge date.
- It is missing required elements. The invoice must identify the container, the period, the amount and its basis, a point of contact for disputes, and a statement of compliance. An invoice that cannot be tied to a specific box and a specific window is not invoice-compliant.
- It went to the wrong party and was not corrected in time. With the addressee section vacated, the practical test is contractual rather than categorical — but a corrected invoice still has to land inside the window to be effective.
- It is a duplicate. The same charge billed twice, or billed by both the carrier and a terminal for the same period, is a billing error regardless of merit.
The mechanism matters because it shifts the burden. In a compliant invoice, the shipper has to argue why the charge is unreasonable. In a non-compliant one, the shipper can simply point at the defect — and the obligation to pay does not exist to be argued about.
The disputes that actually win
Merit-based disputes turn on causation, and there are four categories that regularly succeed, all of them about who caused the delay rather than about whether the charge was calculated correctly.
The terminal was not ready. Cargo not available, a stack not grounded, a berth change that kept the box on board — the clock should not have been running, and the discharge records show it.
No appointment was available. Documented attempts to book a slot, refused or unavailable, over consecutive days. This is the strongest file a consignee can build, and it requires nothing more than screenshots with timestamps.
The carrier caused the delay. A release not issued, a bill of lading corrected late, a container held for a document the carrier itself had to produce. The distinction between “documents were late” and “documents were late because of us” is where these cases are won and lost.
The charge was assessed on the wrong basis. Free time counted from arrival instead of availability, calendar days counted as working days, a holiday that should not have counted. These are arithmetic disputes, and they are usually settled quickly once the underlying records are produced.
Who pays, under which terms
The charge follows the contract, not the cargo, and this is where small sellers get hurt by their own Incoterm.
On a DDP shipment the seller is effectively the importer, so destination demurrage and detention land on the seller even though the consignee controls collection. A seller who offers DDP without controlling the delivery appointment has taken on a cost they cannot influence — which is the strongest commercial argument against DDP for anyone who is not managing the last mile.
On FOB or CIF terms the consignee collects and returns, so the exposure sits with the buyer, and the seller’s problem is limited to origin detention: the box collected for loading and returned late. That is a factory-side discipline question, and it is usually cheap to fix by agreeing a loading window with the supplier.
None of this appears on a freight quotation, which is the recurring theme of how shipping cost is calculated. A forwarder in the middle is normally billed and passes the charge on, which is why a forwarder’s invoice often carries a detention line the shipper never saw from the carrier. Where the underlying invoice was non-compliant, that pass-through does not cure the defect — the same test applies.
Free time is negotiated, not granted
The most expensive misunderstanding in this area is treating free time as a fixed feature of the trade. It is a contract term, and it is one of the few terms available to a small shipper.
Destination free time can be extended in an annual contract, and frequently is — seven days instead of four, or a rate that steps up more slowly. It can also be agreed shipment by shipment for a specific booking, though the leverage is much weaker once the cargo is at sea.
The negotiation that works is blunt and specific: ask for the number of free days at destination, the day the clock starts, whether weekends and holidays count, and what the daily rate becomes after the free period. The same contract that carries these terms usually carries the surcharge caps described in the peak season surcharge piece. Four questions, and most quotations answer none of them — which tells you what will happen if the container is delayed.
The five-line file that ends the argument
Disputes are won on records created before anyone knew there would be a dispute. Five things, collected at the time, settle most of them.
- The availability notice, with its timestamp — the moment the terminal said the box could be collected.
- Appointment attempts, screenshots with dates, including refusals and the absence of slots.
- The gate-in and gate-out records for both the laden and the empty move.
- The invoice itself, kept in full, because the missing element is the argument.
- Your own timeline, one line per event, in order. A single page of dates is more persuasive than a paragraph of explanation.
None of this reduces the charge when the delay is genuinely yours, and it should not. It does something more useful: it makes the charge predictable, and it separates the delays you cause from the ones you inherited — which, given how much of this cost is generated by congestion, appointments and paperwork rather than by cargo, is most of the value.
Both clocks usually start together, and they start because of a document rather than a truck: a late release begins the storage and the rental on the same morning.
Rental is only one of the lines that start moving at discharge: the rest of the invoice is a stack of separate services from five organisations, and each has its own trigger.
Detention runs until the empty is back, not until the cargo is delivered: the return leg is the half of the loop nobody schedules, and it is where the second clock keeps running.
Free time and detention are decided by where a container stands and who holds it; the starting time for each of those clocks comes from a lift in a crane sequence, not from the ship arrival notice.
Free time starts when a box becomes available, not when the ship arrives; available and reachable are nevertheless two different records, and the rehandle log is the one that explains a wasted truck visit.
Arithmetic disputes turn on whether free time counted from arrival or availability; the same choice of start event changes a dwell figure without changing a single event row in any system.
A box that waits at the terminal and a consignment that waits at the freight station run on two clocks; who pays for the wait depends on which list the wait is on.